New Kasteli airport in Crete reaches 70% completion, minister says

New Kasteli airport in Crete reaches 70% completion, minister says

Construction of the new international airport at Kasteli, in Crete, has reached 70% completion, according to Infrastructure and Transport Minister Christos Dimas. The minister presented the progress of the airport and several other major infrastructure projects at a conference held by the newspaper Eleftheros Typos.

Dimas spoke on Tuesday, 24 November, in a discussion with the president of the Technical Chamber of Greece (TEE), Giorgos Stasinos, moderated by journalist Haris Ntigridakis. He addressed increased construction activity nationwide and the challenges involved in delivering the projects, pointing to the use of public and European funds, Public-Private Partnerships (PPPs), and private donations as financing tools.

North Road Axis of Crete: new sections delivered

On the North Road Axis of Crete (VOAK), the first 10 kilometers of the Agios Nikolaos–Neapoli section have been delivered, Dimas said. The Chania bypass is expected to be delivered in the coming weeks, he added, with corresponding work in Rethymno and Heraklion to follow.

Dimas also said road safety measures have been completed along 131 kilometers between Kissamos and Heraklion. According to the minister, no accidents have been recorded this year at the points where these measures were applied.

The minister described the parallel development of air and road infrastructure as a key factor in handling increased tourist traffic to Crete.

Thessaloniki Flyover targets May 2027 opening

In Thessaloniki, the Flyover elevated road has also reached 70% construction progress, with operations targeted to begin in May 2027, Dimas said. The project is expected to double peak-hour vehicle capacity on the route, from 5,000 to 10,000 vehicles.

Regarding the Thessaloniki Metro, the minister said the main line had already reduced city-center vehicle traffic by 10% before the extension to Kalamaria. Studies have begun for a further extension of the network toward the city’s northwestern areas, he added.

Attica and regional projects

For Attica, planning includes a road connection between Elefsina and Oinofyta, for which discussions with the European Commission are under way, as well as construction of the Triple Junction at Skaramagkas. The minister said the Metamorfosi Junction intervention is expected to be completed within the coming weeks.

In the regions, Dimas highlighted road projects linking Kalamata, Rizomylo, Pylos and Methoni, the Chalkida bypass, and connections between Bralos and Amfissa, Thessaloniki and Edessa, Drama and Amfipoli, and Ioannina and Kakavia, citing their relevance to tourist connectivity. He also referred to maintenance of the Egnatia Odos highway and the need to upgrade the safety of existing infrastructure.

Infrastructure tied to tourism growth

The minister said completion of the large transport projects matters for Greek tourism, since accessibility, safety and reliable transport directly affect the visitor experience. For destinations such as Crete, Thessaloniki and Messinia, the new infrastructure could support broader tourism activity, better links between individual destinations, and new investment, he said.

Dimas said the remaining priorities are completing the projects on schedule, keeping within budget, and maintaining the infrastructure over the long term so that the development benefits last.